More than 180 businesses Monday filed a proposed class-action lawsuit against Lone Prairie Electric*, alleging that years of recurring circuit failures have cost companies millions of dollars in lost revenue, damaged equipment and disrupted operations across one of the region’s fastest-growing commercial corridors.
The lawsuit claims the utility repeatedly repaired the same overloaded distribution circuits while postponing broader infrastructure upgrades that engineers had long identified as necessary.
The plaintiffs range from manufacturers and cold-storage warehouses to medical clinics, grocery stores and technology companies. Several businesses reported suffering multiple outages over the past two years, forcing production shutdowns, equipment resets and costly delays.
“It’s not one outage that hurts. It’s the uncertainty. We can’t tell customers we’ll deliver on time when we don’t know whether we’ll have power.”
Miguel Herrera*, chief operating officer of a regional food processing company and one of the lead plaintiffs.
The Chamber of Commerce said repeated reliability problems are becoming an economic development issue, particularly as manufacturers and data-intensive industries continue expanding across the region.
Lone Prairie Electric* said it had not yet reviewed the lawsuit. Speaking on condition of anonymity, a company official acknowledged that maintaining reliability has become increasingly difficult as rapid growth, aging infrastructure and rising electricity demand place unprecedented pressure on local distribution networks.
Experts say those pressures are exposing the limits of traditional capital planning.
For decades, many utilities evaluated transmission, distribution, vegetation management and asset replacement as separate programs. Today, leading utilities are increasingly integrating those decisions, comparing investments across the entire system to determine which projects reduce the greatest amount of operational and customer risk.
Utilities including a Western electric utility and a North American utility have adopted integrated investment planning from IFS Copperleaf to evaluate competing priorities, coordinate projects across departments and reduce unnecessary customer interruptions by combining work on the same parts of the network.
The lawsuit argues that such planning is no longer simply good management but is a business necessity.
“If the grid isn’t reliable,” Lisa Nguyen*, owner of Riverfront Market*, a shopping mall, said, “the local economy isn’t reliable either.”